Midway through a project's execution phase, a team member proposes changes to provide more flexibility and additional features. Project requirements define only the need for a simple solution that is less flexible. Implementing these changes will result in a delay. What should the project manager do?
A. Reject the proposal, and follow the project management plan.
B. Escalate it to the project sponsor via a change request.
C. Agree to the changes, and arrange for more resources at maintain the schedule.
D. Incorporate the changes, and update the project management plan.
在项目执行阶段中途一名团队成员提出变更建议,能提供更多的灵活性和额外功能。项目需求定义仅需要具有较少灵活性的简单解决方案,而实施这些变更将导致延期。项目经理应该怎么做?
A.拒绝该建议,并遵循项目管理计划。
B.通过变更请求将该问题上报给项目发起人。
C.同意变更,并安排更多的资源来保持进度计划。
D.包含变更,并更新项目管理计划。
2018年04月26日 02点04分
1
A. Reject the proposal, and follow the project management plan.
B. Escalate it to the project sponsor via a change request.
C. Agree to the changes, and arrange for more resources at maintain the schedule.
D. Incorporate the changes, and update the project management plan.
在项目执行阶段中途一名团队成员提出变更建议,能提供更多的灵活性和额外功能。项目需求定义仅需要具有较少灵活性的简单解决方案,而实施这些变更将导致延期。项目经理应该怎么做?
A.拒绝该建议,并遵循项目管理计划。
B.通过变更请求将该问题上报给项目发起人。
C.同意变更,并安排更多的资源来保持进度计划。
D.包含变更,并更新项目管理计划。