A company is planning to develop a new product. Project stakeholders come from different
countries and regions, speak various languages, and have diverse political and cultural
backgrounds.What should be a priority for the project manager when developing the
communications management plan?
A. Information confidentiality and sensitivity
B. Project environment
C. The number of communication channels
D. Technological availability
某个公司计划进行一个产品开发项目。干系人来自不同的国家及地区,使用不同的母语
语言,拥有不同的政治及文化背景。项目经理在制定沟通计划时应优先考虑下列哪项因素?
A.信息的保密和敏感度
B.项目环境
C.沟通渠道的数量
D.技术的可用性
2018年10月15日 03点10分
1
countries and regions, speak various languages, and have diverse political and cultural
backgrounds.What should be a priority for the project manager when developing the
communications management plan?
A. Information confidentiality and sensitivity
B. Project environment
C. The number of communication channels
D. Technological availability
某个公司计划进行一个产品开发项目。干系人来自不同的国家及地区,使用不同的母语
语言,拥有不同的政治及文化背景。项目经理在制定沟通计划时应优先考虑下列哪项因素?
A.信息的保密和敏感度
B.项目环境
C.沟通渠道的数量
D.技术的可用性